Project Status

Latest Updates

The project commenced in September 2015 and has made good progress. Planning and permitting have been secured for the site, and waste supply and gas offtake have been agreed, along with carbon dioxide sales. The detailed design has been developed and orders for long lead time items placed.  The project is on track to complete construction by the end of 2017 for delivery of 1 million kilogrammes of BioSNG during 2018.

Document links:

Project progress reports