The BioSNG Commercial Demonstration project is progressing well and the plant should start operation in the second half of 2018.

Civils work is nearly complete and equipment is starting to arrive. ADI, who are responsible for mechanical and electrical integration, have been on site for a month now. Britannia Construction, the civils contractor, are due to complete their work in the next week.

Equipment is being manufactured across the UK and beyond. The wet gas cleaning equipment is being assembled in Surrey and will arrive on site in September while methanation equipment will be brought down from Liverpool in October. The gasifier will ship from the US in two months’ time and will be the last package on site when it arrives in November.

All of the project partners and funders are pleased with progress to date. Click here to find out more about the project.